Further to the answer to question S2W-9476 by Hugh Henry on 28 July 2004, who met the costs of this staff commitment and what those costs w…

Answered Asked by Linda Fabiani SNP Lodged 28 Sep 2004

The question

To ask the Scottish Executive, further to the answer to question S2W-9476 by Hugh Henry on 28 July 2004, who met the costs of this staff commitment and what those costs were.

The answer

Answered by Cathy Jamieson on 19 Oct 2004 · 21 days after it was lodged, on time

I have asked Tony Cameron, Chief Executive of the Scottish Prison Service to respond. His response is as follows:
The costs of the escort service were part of the monthly payment paid to Kilmarnock Prison Services Ltd (KPSL) by the SPS.
SPS do not have details of the staff costs. These are a matter for KPSL.