Further to the answer to question S2W-6813 by Nicol Stephen on 5 April 2004, what (a) track and signalling and (b) station incremental outp…
The question
To ask the Scottish Executive, further to the answer to question S2W-6813 by Nicol Stephen on 5 April 2004, what (a) track and signalling and (b) station incremental output statements are currently being prepared jointly by it and the Strategic Rail Authority for possible future implementation.
The answer
None. The development and approval of such schemes remains a matter for the Strategic Rail Authority.
In the Official Report
No contribution in the Official Report cites S2W-10694 by reference.