Written Question · S2W-10113 · Session 2
Who will meet any capital and additional revenue costs of using underground cables for wind farm output transmission.
The question
To ask the Scottish Executive who will meet any capital and additional revenue costs of using underground cables for wind farm output transmission.
The answer
Capital costs associated with installing and maintaining the electricity transmission infrastructure fall to be met in the first instance by the electricity transmission companies. The activities of these monopoly companies are regulated and the Office for Gas and Electricity Markets (OFGEM) has to be satisfied that the investment is necessary before the costs can be recovered from consumers.
In the Official Report
No contribution in the Official Report cites S2W-10113 by reference.