Further to the answer to question S2W-9052 by Allan Wilson on 28 June 2004, whether the cost of the Scottish Natural Heritage headquarters …

Answered Asked by Fergus Ewing SNP Lodged 29 Jun 2004

The question

To ask the Scottish Executive, further to the answer to question S2W-9052 by Allan Wilson on 28 June 2004, whether the cost of the Scottish Natural Heritage headquarters is an operational matter for Scottish Natural Heritage and, if not, what the cost of the building is estimated to be and whether the costs will be met from public funds.

The answer

Answered by Allan Wilson on 5 Jul 2004 · 6 days after it was lodged, on time

Scottish Natural Heritage (SNH) is responsible for planning and implementing the relocation of its Edinburgh headquarters to Inverness. SNH submitted a project plan covering all aspects of the relocation which ministers accepted as a basis for SNH to develop their tender specification for the new HQ building. SNH issued invitations to tender on 11 June and the budget for procurement of the accommodation will be set after the tenders have been received and evaluated. The costs of the relocation will be funded by additional grant-in-aid from the Scottish Executive.

In the Official Report