Further to the answer to question S2W-8221 by Nicol Stephen on 10 June 2004, when the phase 1 project at Waverley Station is due to commenc…

Answered Asked by Kenny MacAskill SNP Lodged 15 Jun 2004

The question

To ask the Scottish Executive, further to the answer to question S2W-8221 by Nicol Stephen on 10 June 2004, when the phase 1 project at Waverley Station is due to commence and be completed; whether further capacity enhancements are planned for subsequent phases and, if so, what their nature is, what additional services they will provide and when they are scheduled to take place.

The answer

Answered by Nicol Stephen on 2 Jul 2004 · 17 days after it was lodged, 3 days after it was due

Initial planning for the projecthas begun. Detailed design and development work will commence in August of thisyear and conclude by November 2005. It is anticipated that the project will be completedby the end of 2007. The project provides a common first stage for further stationredevelopment options. No decisions have yet been taken about these options.

In the Official Report