Further to the answer to question S2W-1869 by Cathy Jamieson on 9 September 2003, what the distinction is between the contract monthly targ…

Answered Asked by Michael Matheson SNP Lodged 21 May 2004

The question

To ask the Scottish Executive, further to the answer to question S2W-1869 by Cathy Jamieson on 9 September 2003, what the distinction is between the contract monthly target standard that has been removed from appendix A of Schedule 2 to Contract between The Scottish Ministers and Reliance Secure Task Management Ltd for the Provision of Prisoner Escort & Court Custody Services in Scotland and the quarterly baseline points total in paragraph 3 of Schedule F to Minute of Agreement between the Secretary of State for Scotland and Kilmarnock Prison Services Limited for the Design, Construction, Management and Financing of a Prison at Kilmarnock.

The answer

Answered by Cathy Jamieson on 8 Jun 2004 · 18 days after it was lodged, on time

I have asked Tony Cameron, Chief Executive of the Scottish Prison Service to respond. His response is as follows:
The two contracts are with different service providers for different services and were concluded at different times.

In the Official Report