Written Question · S2W-08105 · Session 2
Whether #23.64 million, the agreed cost of the Skye Bridge at July 1990 prices, has been collected in tolls and, if not, when it estimates …
The question
To ask the Scottish Executive whether #23.64 million, the agreed cost of the Skye Bridge at July 1990 prices, has been collected in tolls and, if not, when it estimates that this figure will be reached.
The answer
The agreed costs have not yetbeen recovered through tolling. Information on this issue and the detailed termsof the contract itself, are now the subject of commercially confidential negotiationswith Skye Bridge Limited, with a view to ending the discredited toll regime forthe Skye Bridge.
In the Official Report
No contribution in the Official Report cites S2W-08105 by reference.