Written Question · S2W-07638 · Session 2
What information it has in respect of the plant margin of electricity generation in relation to estimated peak demand for electricity, in l…
The question
To ask the Scottish Executive what information it has in respect of the plant margin of electricity generation in relation to estimated peak demand for electricity, in light of its renewable energy targets.
The answer
Installed capacity for electricitygeneration in Scotland currently amounts to around 10 Gigawatts (GW). Peak electricitydemand in Scotland is currently estimated at around 6 GW.
In the Official Report
No contribution in the Official Report cites S2W-07638 by reference.