Written Question · S2W-07353 · Session 2
Further to the answer to question S2W-6589 by Mrs Mary Mulligan on 11 March 2004, what the remaining #170 million from the initial budget o…
The question
To ask the Scottish Executive, further to the answer to question S2W-6589 by Mrs Mary Mulligan on 11 March 2004, what the remaining #170 million from the initial budget of #350 million for the delivery of the free central heating programme has been spent on.
The answer
I have asked Angiolina Foster, the Chief Executive of Communities Scotland to respond. Her response isas follows:
£350 million wasa 2001 estimate of the cost of providing the central heating programme, derivedfrom information looking back to 1996. This has since been revised leading tothe estimated cost being reduced to £180 million.
The original commitmentremains in place that funding is being made available to ensure that anyapplicant who meets the eligibility criteria set out in the central heatingprogramme, and comes forward before the programme’s close, will receive acentral heating system.
£350 million wasa 2001 estimate of the cost of providing the central heating programme, derivedfrom information looking back to 1996. This has since been revised leading tothe estimated cost being reduced to £180 million.
The original commitmentremains in place that funding is being made available to ensure that anyapplicant who meets the eligibility criteria set out in the central heatingprogramme, and comes forward before the programme’s close, will receive acentral heating system.
In the Official Report
No contribution in the Official Report cites S2W-07353 by reference.