Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S2W-07101 · Session 2

Further to the answers to questions S2W-6588 and S2W-6589 by Mrs Mary Mulligan on 11 March 2004, what the reasons are for the increase in t…

Answered Asked by John Swinburne SSCUP Lodged 19 Mar 2004

The question

To ask the Scottish Executive, further to the answers to questions S2W-6588 and S2W-6589 by Mrs Mary Mulligan on 11 March 2004, what the reasons are for the increase in the final cost to #180 million and the completion date being 2007 for the free central heating programme, in light of forecasts given in December 2003 of #108 million and 2006 respectively.

The answer

Answered by Mary Mulligan on 1 Apr 2004 · 13 days after it was lodged, on time

I have asked Angiolina Foster, the Chief Executive of Communities Scotland to respond. Her response isas follows:
The completion of the centralheating programme is set at:
April 2004 for local authorities;
during 2004 for housing associations;
April 2006 for the private sector; and,
because of the numbers involved, March 2007 forGlasgow Housing Association.
There has been no increasein the estimated final cost of the central heating programme, which remains at£180 million. The £108 million figure relates only to that part of the programmerelating to the private sector.

In the Official Report

No contribution in the Official Report cites S2W-07101 by reference.