When it will make an announcement on the proposal to build a 3.5 megawatt hydroelectric generating station at Shieldaig/Slattadale, Wester …

Answered Asked by Maureen Macmillan Lab Lodged 15 Mar 2004

The question

To ask the Scottish Executive when it will make an announcement on the proposal to build a 3.5 megawatt hydroelectric generating station at Shieldaig/Slattadale, Wester Ross.

The answer

Answered by Lewis Macdonald on 16 Mar 2004 · 1 day after it was lodged, on time

I can announce that the Scottishministers have refused consent to this proposal in terms of section 36 of theElectricity Act 1989.
This announcement follows alengthy consultation process which involved environmental groups, governmentbodies and members of the public.

In the Official Report

No contribution in the Official Report cites S2W-06962 by reference.