Further to the answers to questions S2W-5973 and S2W-5975 by Ms Margaret Curran on 1 March 2004, what steps will be taken in the short term…

Answered Asked by Christine Grahame SNP Lodged 2 Mar 2004

The question

To ask the Scottish Executive, further to the answers to questions S2W-5973 and S2W-5975 by Ms Margaret Curran on 1 March 2004, what steps will be taken in the short term to ensure that homeless people in East Lothian receive adequate services whilst East Lothian Council produces its improvement plan and during implementation of the plan once approved by Communities Scotland.

The answer

Answered by Margaret Curran on 16 Mar 2004 · 14 days after it was lodged, on time

I have asked Angiolina Foster, Chief Executive of Communities Scotland, to respond. Her response is asfollows:
Scottish Ministers actingthrough Communities Scotland now require East Lothian Council to take action toensure that homeless people in its area receive adequate services. The council’simprovement plan, setting out how it will respond to the findings of thePathfinder Inspection Report is due to be submitted on 17 March 2004.
Communities Scotlandexpects this to contain immediate, short term and longer term actions toprogress improvements. The agency will then agree arrangements with the localauthority for monitoring the implementation of the plan to ensure that thenecessary improvements in the services for homeless people and those threatenedwith homelessness are achieved. Performance in this area will be reassessedwithin two years and a full re-inspection of the local authority will becarried out within five years.

In the Official Report