Written Question · S2W-04505 · Session 2
Further to answer to question S2W-3452 by Nicol Stephen on 12 November 2003, what the 12 road projects referred to in the answer are, showi…
The question
To ask the Scottish Executive, further to answer to question S2W-3452 by Nicol Stephen on 12 November 2003, what the 12 road projects referred to in the answer are, showing in each case the (a) road, (b) part of the road being upgraded and (c) total amount of spending from (i) local authorities and (ii) European structural funds.
The answer
The twelve road projects fundedfrom European Structural Funds are listed below with the associated local authoritycontributions to each project. Other local authority roads expenditure, given inthe Provisional Outturn Estimate, is managed locally.
Road Being Upgraded
| European Structural Funds Award
| Local Authority Contribution
| Total
Strategic timber transportation road network for Argyll (25.2 km of public road).
| £730,820
over 5 years
| £742,404
| £1,473,224
Arran economic enhancement project (phase 1) road improvements. Including upgrading sections of A841 Brodick- Corrie- Lochranza and the B880 Brodick to Blackwaterfoot.
| £166,000
over 1 year
etc
| £635,000
| £801,000
A832 Achnasheen to Kinlochewe.
| 710
over 2 years
| 2130
| 2840
A851 Broadford to Armadale (phases 3,4,5).
| 1,816.6
over 5 years
| 7,266.4
| 9083
Gartcosh regeneration phase 2 link road and access corridor reclamation.
| 1,490
| 1,200
| 2690
Glasgow harbour transport Infrastructure.
| 3,844.37
| 192
| 4036.37
Inchinnan business park access road completion and structural landscaping.
| 782.60
| 0
| 782.6
Gartcosh access road.
| 282.15
| 282.15
| 564.3
Inchinnan access road phase 1.
| 526.64
| 0
| 526.64
West of Scotland Science Park road access phases 3 and 4.
| 315.72
| 0
| 315.72
Objective 2 South – projects including realignment of r
Road Being Upgraded
| European Structural Funds Award
| Local Authority Contribution
| Total
Strategic timber transportation road network for Argyll (25.2 km of public road).
| £730,820
over 5 years
| £742,404
| £1,473,224
Arran economic enhancement project (phase 1) road improvements. Including upgrading sections of A841 Brodick- Corrie- Lochranza and the B880 Brodick to Blackwaterfoot.
| £166,000
over 1 year
etc
| £635,000
| £801,000
A832 Achnasheen to Kinlochewe.
| 710
over 2 years
| 2130
| 2840
A851 Broadford to Armadale (phases 3,4,5).
| 1,816.6
over 5 years
| 7,266.4
| 9083
Gartcosh regeneration phase 2 link road and access corridor reclamation.
| 1,490
| 1,200
| 2690
Glasgow harbour transport Infrastructure.
| 3,844.37
| 192
| 4036.37
Inchinnan business park access road completion and structural landscaping.
| 782.60
| 0
| 782.6
Gartcosh access road.
| 282.15
| 282.15
| 564.3
Inchinnan access road phase 1.
| 526.64
| 0
| 526.64
West of Scotland Science Park road access phases 3 and 4.
| 315.72
| 0
| 315.72
Objective 2 South – projects including realignment of r