Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S2W-02181 · Session 2

Which of the costings given for infrastructure commitments in A Partnership for a Better Scotland are index-linked.

Answered Asked by Kenny MacAskill SNP Lodged 26 Aug 2003

The question

To ask the Scottish Executive which of the costings given for infrastructure commitments in A Partnership for a Better Scotland are index-linked.

The answer

Answered by Andy Kerr on 4 Sep 2003 · 9 days after it was lodged, on time

The costings given in A Partnership for a Better Scotland – as is also the convention for all Executive financial publications – are given in cash terms:in other words, they are not index-linked unless specifically identified as such.
In part this is because the UK Government uses cash numbers for setting the overall control total and in its publications. Having our published numbers on a consistent basis improves transparency. Since our budget is fixed in cash terms, index-linking particular items would also risk breaching the overall budget should inflation prove higher than forecast.

In the Official Report

No contribution in the Official Report cites S2W-02181 by reference.