Written Question · S2W-00866 · Session 2
Further to the answer to question S2W-148 by Nicol Stephen on 2 June 2003, whether there are any concerns about implications for the comple…
The question
To ask the Scottish Executive, further to the answer to question S2W-148 by Nicol Stephen on 2 June 2003, whether there are any concerns about implications for the completion date of the Aberdeen western peripheral route if Aberdeen City Council proceeds with an additional road crossing over the River Don.
The answer
I refer the member to the answer given to question S2W-104 on 6 June 2003. No implications for the proposed completion date are envisaged. All answers to written parliamentary questions are available on the Parliament's website, the search facility for which can be found at http://www.scottish.parliament.uk/webapp/search_wa.
In the Official Report
No contribution in the Official Report cites S2W-00866 by reference.