Parliament Workbench
Data: Motions & questions to 19 Nov 2026

SPCB Written Question · S2W-00662 · Session 2

Further to the answer to question S1W-21898 by Sir David Steel on 24 January 2002, on what date the construction managers obtained each doc…

Answered Asked by Fergus Ewing SNP Lodged 5 Jun 2003

The question

To ask the Presiding Officer, further to the answer to question S1W-21898 by Sir David Steel on 24 January 2002, on what date the construction managers obtained each document referred to in the answer; from whom they were obtained, and from whom, and on what dates, the construction managers sought credit reference information in respect of Flour City Architectural Metals (UK) Ltd.

The answer

Answered by George Reid on 9 Jul 2003 · 34 days after it was lodged, 20 days after it was due

The Construction Managers for the Holyrood project, Bovis Lend Lease (Scotland) Ltd, have informed the Project Team that all the documents listed in the answer to parliamentary question S1W-21898 on 24 January 2002, were received from Flour City Architectural Metals (UK) Ltd, during the prequalification process for the bid list for the MSP Building Cladding package. That process took place in May 2000.Bovis Lend Lease (Scotland) Ltd have also advised that, as Flour City Architectural Metals (UK) Ltd had only been operating in the UK for a short period of time, no published credit references were available.

In the Official Report

No contribution in the Official Report cites S2W-00662 by reference.