Written Question · S1W-34608 · Session 1
Further to the answer to question S1W-33691 by Lewis Macdonald on 25 February 2003, what body will be responsible for carrying out the perf…
The question
To ask the Scottish Executive, further to the answer to question S1W-33691 by Lewis Macdonald on 25 February 2003, what body will be responsible for carrying out the performance impact studies and issuing of regulatory dispensations for each rail project and what impact a negative study or non-issue of such dispensation would have on each project.
The answer
Network Rail in partnership with the promoter are responsible for assessing the impact on operational performance of rail projects. Together, they agree bilaterally on the impact of projects and submit their calculations to The Office of the Rail Regulator (ORR) to evaluate. The ORR in consultation with the Strategic Rail Authority has the power to adjust/reset benchmarks accordingly.