To ask the Scottish Executive, further to the answer to question S1O-6561 by Iain Gray on 6 March 2003, why it could not proceed on a design and construct fixed-cost tender basis for the improvements on the southern section of the A77.
The answer
It would not be possible at this stage to define the scope of a potential fixed-cost, fixed-time contract. Contracts of this type involve higher tendering costs and longer tendering periods, and the decision as to which type of contract to employ on any scheme must balance this against the scale of costs and potential savings.