The question

To ask the Scottish Executive, further to the answer to question S1O-6561 by Iain Gray on 6 March 2003, how long the public consultation process will take after receipt of the successful preliminary design proposals for the A77 southern section improvements.

The answer

Answered by Lewis Macdonald on 25 Mar 2003 · 18 days after it was lodged, 4 days after it was due

The duration of the public consultation period prior to the finalisation of the necessary statutory processes will depend on public reaction to proposals once they have been published.