Written Question · S1W-33681 · Session 1
What procedures were in place at the time of construction in order to identify construction defects such as those now identified as affecti…
The question
To ask the Scottish Executive what procedures were in place at the time of construction in order to identify construction defects such as those now identified as affecting housing in Ainslie Road and Maclehose Road, Cumbernauld; who had responsibility for ensuring that any such procedures were followed, and why the defects were not identified and prevented at the time of construction.
The answer
The underlying construction methods used in the flats at Ainslie Road and Maclehose Road were regarded at the time of the construction of the flats as accepted practice. The building of these properties would have been subject to the standards and inspection processes required by the local byelaws or the building regulations as they applied at the time.
In the Official Report
No contribution in the Official Report cites S1W-33681 by reference.