Further to the answer to question S1W-32002 by Lewis Macdonald on 10 December 2002, when a response to the A737/A738 Route Accident Reducti…
The question
To ask the Scottish Executive, further to the answer to question S1W-32002 by Lewis Macdonald on 10 December 2002, when a response to the A737/A738 Route Accident Reduction Plan will be published.
The answer
The recommendations of the A737/A738 Route Accident Reduction Plan have been accepted in full. The works include:Provision of a pedestrian crossing on A737 at Kilwinning Academy/Abbey Primary School.Red textured bar markings and triangular school children warning signs on A737 carriageway on both approaches to schools.Provision of a new bus lay-by on east side of A737, south of Kilwinning Academy.Installation of advance stop lines, kerb realignment, skid resistant surfacing, carriageway markings, textile paving and high visibility guard-rail at A737/A738 Dalry Road/Byres Road Junction.Provision of a pedestrian crossing on A738 Stevenston Road (exact location to be identified).Installation of right turn ghost island markings and centre road hatching on westbound approach to A738 Stevenston Road/Castlehill Road Junction.Various amendments/renewals of existing signs on the A737/A738 through Kilwinning.It is intended that the works will be implemented by end of March 2003.
In the Official Report
No contribution in the Official Report cites S1W-32569 by reference.