Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S1W-31679 · Session 1

Further to the answer to question S1W-11310 by Mr Sam Galbraith on 30 November 2000, how many applications for flood prevention and coast p…

Answered Asked by Margaret Ewing SNP Lodged 19 Nov 2002

The question

To ask the Scottish Executive, further to the answer to question S1W-11310 by Mr Sam Galbraith on 30 November 2000, how many applications for flood prevention and coast protection schemes have been (a) approved and (b) rejected, broken down by name of applicant, nature of project and amount sought and, where applicable, awarded; whether it will give a progress report on each successful application, detailing the likely completion date for the project, and what the reasons were for any applications being rejected.

The answer

Answered by Allan Wilson on 22 Nov 2002 · 3 days after it was lodged, on time

Further to the additional funding announced by Mr Galbraith, in the answer given to question S1W-11310, I can confirm that all applications for the additional funds referred to have been met in full. No requests have been declined. Additional funding has been provided for the following schemes:Scheme | Year
2001-02(£ million) | 2002-03(£ million) | 2003-04(£ million)
River Kelvin FPS | 5.25 | 4.25 |
Johnston FPS | 1.00 | |
Wemyss Villages CPS | 2.25 | |
Crosslee FPS | | 1.50 |
Linlithgow FPS | | 0.20 | 0.90
Total | 8.5 | 5.95* | 0.90*
Note:*Part-year totals only.The balance of the additional funding for years 2002-03 and 2003-04 remains to be allocated.All the schemes are complete or virtually complete, with the exception of the Linlithgow Flood Prevention Scheme which is planned to commence construction in 2003.

In the Official Report

No contribution in the Official Report cites S1W-31679 by reference.