SPCB Written Question · S1W-30287 · Session 1
What the reasons are for the additional cost of the works packages let as part of the Holyrood Project and set out in Annex A to the quarte…
The question
To ask the Presiding Officer what the reasons are for the additional cost of the works packages let as part of the Holyrood Project and set out in Annex A to the quarterly report on the Parliament Building Project to be considered at the Finance Committee on 8 October 2002 and, in particular, how much of the additional cost for each package is attributable, or estimated as being attributable, to (a) blast resistance requirements and (b) other reasons, detailing in full what the reasons are for the additional costs in each case.
The answer
As reported to the Finance Committee on 8 October 2002, the Holyrood Project Team are currently in the process of compiling a more detailed estimate of the additional costs associated with the blast resistance requirements for the new building. The Convener of the Holyrood Progress Group has confirmed that the results of this exercise will be made available in due course.
In the Official Report
No contribution in the Official Report cites S1W-30287 by reference.