The question
To ask the Scottish Executive, further to the answer to question S1W-24752 by Lewis Macdonald on 16 May 2002, whether it will issue an updated profile of its projected trunk roads programme and identify all proposed additional projects, in the light of the revised budgetary allocations set out in Building a Better Scotland
- Spending Proposals 2003-06: What the money buys.
The answer
Total expenditure on the trunk road programme from 2002-03 to 2005-06 is set out on page 46 of Building a Better Scotland. Detailed level 3 allocations have yet to be determined. The overall allocations include additional resources for preparation of the A8 and A80 motorway upgrades.