Written Question · S1W-27445 · Session 1
Further to the answer to question S1W-26711 by Lewis Macdonald on 5 July 2002, what the cost of commissioning and obtaining the Direct Air …
The question
To ask the Scottish Executive, further to the answer to question S1W-26711 by Lewis Macdonald on 5 July 2002, what the cost of commissioning and obtaining the Direct Air Services Action Plan was; who commissioned the report, and how any routes proposed in the report would be funded.
The answer
Scottish Enterprise commissioned the Direct Air Services Action Plan at a cost of £50,000. The plan, which was completed in January 2000, was developed to analyse the viability of, and identify opportunities for, new routes to/from Scotland. The information was made available to airlines and airport operators. It is for the Executive's agencies (Scottish Enterprise and VisitScotland) to decide how best any available funding can be deployed for the greatest benefit of the Scottish economy and tourism.
In the Official Report
No contribution in the Official Report cites S1W-27445 by reference.