SPCB Written Question · S1W-27186 · Session 1
Further to his answer to question S1W-26404 on 11 June 2002, who was responsible for commissioning the due diligence procedures on Flour Ci…
The question
To ask the Presiding Officer, further to his answer to question S1W-26404 on 11 June 2002, who was responsible for commissioning the due diligence procedures on Flour City Architectural Metals (UK) Ltd and whether the procedures were completed prior to the issuing of the contract.
The answer
The Construction Manager, Bovis Lend Lease (Scotland) Limited, was responsible for conducting due diligence procedures, which were completed before the contract was awarded.
In the Official Report
No contribution in the Official Report cites S1W-27186 by reference.