SPCB Written Question · S1W-26696 · Session 1
Further to his answer to question S1W-26404 on 12 June 2002, what indemnity arrangements were put in place in regard to the contract with F…
The question
To ask the Presiding Officer, further to his answer to question S1W-26404 on 12 June 2002, what indemnity arrangements were put in place in regard to the contract with Flour City Architectural Metals (UK) Ltd.
The answer
The only form of indemnity put in place in regard to the contract with Flour City Architectural Metals (UK) Ltd was the Parent Company Guarantee.
In the Official Report
No contribution in the Official Report cites S1W-26696 by reference.