Further to his answer to question S1W-26404 on 12 June 2002, what indemnity arrangements were put in place in regard to the contract with F…

Answered Asked by Alex Neil SNP Lodged 12 Jun 2002

The question

To ask the Presiding Officer, further to his answer to question S1W-26404 on 12 June 2002, what indemnity arrangements were put in place in regard to the contract with Flour City Architectural Metals (UK) Ltd.

The answer

Answered by David Steel on 25 Jun 2002 · 13 days after it was lodged, on time

The only form of indemnity put in place in regard to the contract with Flour City Architectural Metals (UK) Ltd was the Parent Company Guarantee.

In the Official Report

No contribution in the Official Report cites S1W-26696 by reference.