What plans Scottish Water has in place to rectify any failures of the proposed water treatment plant at Milngavie to meet specified removal…

Answered Asked by Des McNulty Lab Lodged 10 Jun 2002

The question

To ask the Scottish Executive what plans Scottish Water has in place to rectify any failures of the proposed water treatment plant at Milngavie to meet specified removal efficiency criteria.

The answer

Answered by Ross Finnie on 24 Jun 2002 · 14 days after it was lodged, on time

Scottish Water has carried out extensive trials on pilot plant to check the performance of the water treatment process proposed for Milngavie. However, should the full scale plant fail to meet all the necessary regulatory standards, then the Drinking Water Quality Regulator will require remedial measures to be put in place.