Written Question · S1W-26499 · Session 1
What the cost to it at March 2001 prices was of the independent engineer engaged to monitor the progress of work on HM Prison Kilmarnock in…
The question
To ask the Scottish Executive what the cost to it at March 2001 prices was of the independent engineer engaged to monitor the progress of work on HM Prison Kilmarnock in accordance with section 11.4 of the Minute of Agreement between the Secretary of State for Scotland and Kilmarnock Prison Services Limited for the Design, Construction, Management and Financing of a Prison at Kilmarnock.
The answer
I have asked Tony Cameron, Chief Executive of the Scottish Prison Service to respond. His response is as follows:£194,226, excluding VAT.
In the Official Report
No contribution in the Official Report cites S1W-26499 by reference.