Written Question · S1W-25268 · Session 1
In relation to paragraph 95 of the Scottish Prison Service Estates Review, whether in estimating costs for a publicly built prison, the rev…
The question
To ask the Scottish Executive, in relation to paragraph 95 of the Scottish Prison Service Estates Review, whether in estimating costs for a publicly built prison, the review assumed the adoption of a fixed price construction contract, detailing the reasons for its position on the matter.
The answer
I have asked Tony Cameron, Chief Executive of the Scottish Prison Service to respond. His response is as follows:All construction costs were determined by professional advisers based on best estimates of industry costs, with appropriate risk analysis. Contract type is a matter for a later stage when it would be decided how best to manage all identified risks.
In the Official Report
No contribution in the Official Report cites S1W-25268 by reference.