Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S1W-25031 · Session 1

Further to the answer to question S1W-23036 by Iain Gray on 7 March 2002, what progress was finally made on the target of Eaga Partnership …

Answered Asked by Adam Ingram SNP Lodged 11 Apr 2002

The question

To ask the Scottish Executive, further to the answer to question S1W-23036 by Iain Gray on 7 March 2002, what progress was finally made on the target of Eaga Partnership (Scotland) to install 3,500 heating systems under the Central Heating Installation Programme by March 2002.

The answer

Answered by Margaret Curran on 9 May 2002 · 28 days after it was lodged, on time

Eaga met the target and installed 3,559 central heating systems in 2001-02.

In the Official Report

No contribution in the Official Report cites S1W-25031 by reference.