Further to the answer to question S1W-7588 by Sarah Boyack on 22 June 2000, what the timetable is for the renewal of the Scottish rail pass…

Answered Asked by Des McNulty Lab Lodged 8 Apr 2002

The question

To ask the Scottish Executive, further to the answer to question S1W-7588 by Sarah Boyack on 22 June 2000, what the timetable is for the renewal of the Scottish rail passenger franchise.

The answer

Answered by Lewis Macdonald on 7 May 2002 · 29 days after it was lodged, on time

The timetable for the renewal of the Scottish rail passenger franchise is as follows:the Scottish Executive's Directions and Guidance to the Strategic Rail Authority (SRA) will be issued this summer;
the SRA will subsequently invite bids later in 2002;
initial bids will then be evaluated and short-listed;
short listed bidders will be invited to submit a Best and Final Offer before a preferred bidder is selected, with whom to negotiate a new franchise agreement, and
the new franchise will begin on 1 April 2004.