To ask the Scottish Executive, further to the answer to question S1W-12540 by Mr Jim Wallace on 21 February 2001, what its (a) base case, (b) best case and (c) worst case estimates were for the cost of HM Prison Kilmarnock.
The answer
I have asked Tony Cameron, Chief Executive of the Scottish Prison Service to respond. His response is as follows:The net present value (NPV) of the contract for HMP Kilmarnock was £133 million, based on the agreed contract pricing. The NPV of the public sector comparator was calculated on a pre- and post-risk basis, amounting to £263 million and £290 million respectively.