What the estimated cost is of upgrading the A9 to dual carriageway for the entire section from Perth to Inverness.

Answered Asked by Keith Raffan LD Lodged 6 Mar 2002

The question

To ask the Scottish Executive what the estimated cost is of upgrading the A9 to dual carriageway for the entire section from Perth to Inverness.

The answer

Answered by Lewis Macdonald on 20 Mar 2002 · 14 days after it was lodged, on time

It is not the Executive's policy to dual the whole length of the A9 between Perth and Inverness, and no recent estimate of the costs has been made. However, a study commissioned in 1993 estimated these costs at £281 million at 1994 prices.

In the Official Report

No contribution in the Official Report cites S1W-23802 by reference.