Whether any deadline has been fixed for the submission by Scottish Natural Heritage (SNH) of a report costing the options for relocating it…

Answered Asked by Fergus Ewing SNP Lodged 8 Feb 2002

The question

To ask the Scottish Executive whether any deadline has been fixed for the submission by Scottish Natural Heritage (SNH) of a report costing the options for relocating its headquarters from Edinburgh; which locations are being considered for such a relocation; whether SNH staff will have access to the full report prior to its final submission, and whether any parts of the report will not be disclosed and what the reasons are for the position on this matter.

The answer

Answered by Allan Wilson on 22 Feb 2002 · 14 days after it was lodged, on time

It was announced on 19 November 2001 that Scottish Natural Heritage (SNH) would undertake a relocation review, as there is a property lease break in one of its Edinburgh offices in 2005. The review will access issues such as costs, quality and efficiency of service, economic factors such as unemployment, availability and suitability of property and staff, transport and environmental issues. Staff and unions will be consulted before decisions are taken on the most suitable location for SNH staff. The target date for completion of the review is mid-2002 and ministers will take a decision on the most suitable HQ location for SNH based on the review findings.

In the Official Report