SPCB Written Question · S1W-22708 · Session 1
Further to his answer to question S1W-22107 on 4 February 2002, whether Flour City Architectural Metals (UK) Ltd provided all of the design…
The question
To ask the Presiding Officer, further to his answer to question S1W-22107 on 4 February 2002, whether Flour City Architectural Metals (UK) Ltd provided all of the design services which they were under contractual obligation to provide.
The answer
I understand from the Convener of the Holyrood Progress that Flour City Architectural Metals (UK) Ltd had not completed all of the design services required under contract prior to the company's insolvency.
In the Official Report
No contribution in the Official Report cites S1W-22708 by reference.