Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S1W-22019 · Session 1

Further to the answer to question S1W-21310 by Lewis Macdonald on 16 January 2002, why there has been a delay in the Order in Council under…

Answered Asked by Adam Ingram SNP Lodged 17 Jan 2002

The question

To ask the Scottish Executive, further to the answer to question S1W-21310 by Lewis Macdonald on 16 January 2002, why there has been a delay in the Order in Council under section 30 of the Scotland Act 1998 to transfer legislative competence to the Parliament in respect of the promotion and construction of railways being laid and brought into force.

The answer

Answered by Lewis Macdonald on 8 Feb 2002 · 22 days after it was lodged, 8 days after it was due

Officials from the Scottish Executive and from the Department for Transport, Local Government and the Regions have been working steadily through the details of implementing the McLeish settlement since devolution. Orders implementing previous parts of it have been agreed by both Parliaments. This order constitutes the final step and I expect it to be made in the first half of this year.

In the Official Report

No contribution in the Official Report cites S1W-22019 by reference.