Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S1W-21183 · Session 1

Further to the answer to question S1W-19197 by Iain Gray on 16 November 2001, what the total cost was to it of the tender process in respec…

Answered Asked by Michael Matheson SNP Lodged 17 Dec 2001

The question

To ask the Scottish Executive, further to the answer to question S1W-19197 by Iain Gray on 16 November 2001, what the total cost was to it of the tender process in respect of HM Prison Kilmarnock.

The answer

Answered by Jim Wallace on 25 Feb 2002 · 70 days after it was lodged, 42 days after it was due

I have asked Tony Cameron, Chief Executive of the Scottish Prison Service (SPS) to respond. His response is as follows:SPS did not collect tender cost data in respect of the contract for HM Prison Kilmarnock. Tender costs are not separately identified in any Scottish Prison Service contract.

In the Official Report

No contribution in the Official Report cites S1W-21183 by reference.