Further to his answer to question S1W-19154 on 14 November 2001, on what date Flour City Architectural Metals (UK) Ltd was required to subm…
The question
To ask the Presiding Officer, further to his answer to question S1W-19154 on 14 November 2001, on what date Flour City Architectural Metals (UK) Ltd was required to submit a performance bond; who was responsible for ensuring that Flour City fulfilled that obligation; what steps were taken to seek performance of that obligation and when any such steps were taken; whether the absence of the performance bond will result in sub-contractors of Flour City not receiving payments of their accounts, and whether the principal contractors have any liability towards these sub-contractors.
The answer
The Project's construction manager, Bovis Lend Lease Ltd, actively pursued a performance bond from Flour City Architectural Metals (FCAM) (UK) Ltd, during the period April-July 2001, in anticipation of the full Trade Contract being concluded. Once in place however, the Trade Contract required submission of an agreed performance bond by 17 August 2001. When this was not provided the relevant "notice of failure" was issued on 30 August 2001. Shortly after "notice of failure", a meeting was held with FCAM (International) senior management and a further deadline, of 14 September 2001, was set for provision of a performance bond. This deadline was not met and "notice of intention to terminate contract" was duly issued to FCAM (UK) Ltd on 26 September 2001. The performance bond was a requirement of the contract between the Scottish Parliamentary Corporate Body and FCAM (UK) Ltd, and has no bearing on contracts between FCAM (UK) Ltd and its subcontractors. The SPCB has no contractual liability to FCAM (UK) Ltd's subcontractors.
In the Official Report
No contribution in the Official Report cites S1W-21036 by reference.