The question
To ask the Scottish Executive, further to the answer to question S1W-18697 by Sarah Boyack on 30 October 2001, whether the bid for the work on the A1 Haddington to Dunbar Expressway has been accepted and whether the final contracts have been agreed.
The answer
No, the five contractors selected to tender for the work are due to return their bids on 19 December 2001. The award of contract is expected in the first quarter of 2002.