The question

To ask the Scottish Executive why, under section 2.1 (i) of Schedule 3, Part 4 of the Term Contract for Management and Maintenance of the Scottish Trunk Road Network, Amey Highways Ltd and BEAR (Scotland) Ltd are prevented from responding directly to enquiries from MPs and MSPs and why those groups were so specified.

The answer

Answered by Lewis Macdonald on 10 Dec 2001 · 14 days after it was lodged, on time

This condition, which is no different to that in the previous contracts, was included to define areas of responsibility between the Scottish Executive and the Operating Companies in respect of dealings with MPs and MSPs.