Written Question · S1W-19851 · Session 1
Further to the answer to question S1O-3969 by Sarah Boyack on 1 November 2001, on what date it approved the winter maintenance plans in res…
The question
To ask the Scottish Executive, further to the answer to question S1O-3969 by Sarah Boyack on 1 November 2001, on what date it approved the winter maintenance plans in respect of each trunk roads maintenance contract awarded to AMEY Highways Ltd and BEAR Scotland Ltd and on what date these plans were required to be in place under these contracts.
The answer
The Contract requires the Operating Companies to submit their Winter Maintenance Plans to the Scottish Executive for detailed scrutiny by 31 July 2001.The plans are then scrutinised by the Performance Audit Group and, if necessary, amended or clarified before the Scottish Executive consents to the plans. There is no specified time limit within which the Scottish Executive is required to approve the plans.The Winter Maintenance Plans were consented to by the Scottish Executive on the following dates:Operating Company / Unit | Date Approved
BEAR Scotland Ltd North East Unit | 16 October 2001
BEAR Scotland Ltd North West Unit | 10 October 2001
AMEY Highways LtdSouth East Unit | 5 October 2001
AMEY Highways LtdSouth West Unit | 2 October 2001
BEAR Scotland Ltd North East Unit | 16 October 2001
BEAR Scotland Ltd North West Unit | 10 October 2001
AMEY Highways LtdSouth East Unit | 5 October 2001
AMEY Highways LtdSouth West Unit | 2 October 2001
In the Official Report
No contribution in the Official Report cites S1W-19851 by reference.