Written Question · S1W-19837 · Session 1
Further to the answer to question S1W-18695 by Sarah Boyack on 26 October 2001, whether the delay to the start of the construction of the p…
The question
To ask the Scottish Executive, further to the answer to question S1W-18695 by Sarah Boyack on 26 October 2001, whether the delay to the start of the construction of the proposed A1 expressway between Haddington and Dunbar would be any longer than it currently is expected to be if a local public inquiry was held.
The answer
Yes, a public local inquiry would result in a 12 to 18 month delay to the present rate of progress.
In the Official Report
No contribution in the Official Report cites S1W-19837 by reference.