Further to the answer to question S1W-19385 by Sarah Boyack on 8 November 2001, how much it would cost to modify the proposed A1 expressway…
The question
To ask the Scottish Executive, further to the answer to question S1W-19385 by Sarah Boyack on 8 November 2001, how much it would cost to modify the proposed A1 expressway between Haddington and Dunbar to incorporate slip roads to and from East Linton prior to it being completed.
The answer
I refer the member to the answer given to question S1W-18697 on 26 October 2001. If slip roads could be included within the proposed contract as the result of a successful promotion of a further Variation Scheme, then the costs of including the work in the new contract could fall in the range of £2 to £6 million, depending on the impact of the change of contract specification on the contractors operations.