The question

To ask the Scottish Executive what the cost was of each improvement scheme undertaken on the A9 between Dunkeld and Pitlochry during 1999-2000 and 2000-01 and what the cost will be of any improvement schemes planned for 2001-02.

The answer

Answered by Sarah Boyack on 27 Jun 2001 · 14 days after it was lodged, on time

No improvement schemes were implemented on the A9 between Dunkeld and Pitlochry for financial years 1999-2000 and 2000-01. Expenditure for the current financial year 2001-02 is currently expected to be £40,000.