Written Question · S1W-16258 · Session 1
What the cost was of each improvement scheme undertaken on the A9 between Dunkeld and Pitlochry during 1999-2000 and 2000-01 and what the c…
The question
To ask the Scottish Executive what the cost was of each improvement scheme undertaken on the A9 between Dunkeld and Pitlochry during 1999-2000 and 2000-01 and what the cost will be of any improvement schemes planned for 2001-02.
The answer
No improvement schemes were implemented on the A9 between Dunkeld and Pitlochry for financial years 1999-2000 and 2000-01. Expenditure for the current financial year 2001-02 is currently expected to be £40,000.
In the Official Report
No contribution in the Official Report cites S1W-16258 by reference.