Written Question · S1W-15620 · Session 1
Further to the answer to question S1W-13189 by Nicol Stephen on 20 March 2001, what progress has been made regarding the provision and fund…
The question
To ask the Scottish Executive, further to the answer to question S1W-13189 by Nicol Stephen on 20 March 2001, what progress has been made regarding the provision and funding of pre-school placements for children whose fourth birthday falls in January or February and whose parents wish to defer entry to primary school until after the children reach the age of five.
The answer
I accept the five key recommendations in the report of the Deferrals Working Group submitted to me in December 2000. CoSLA and ADES also support them.From August 2001, children who become four in January or February and who, though eligible to start school, have their entry to primary school deferred by their parents will be able to access an additional year of publicly funded pre-school education.Local authorities will retain discretion over the provision of additional pre-school education for slightly older children
- those born between September to December
- whose parents are considering deferral.CoSLA and ADES will improve information for parents considering deferral. They will also develop guidance for local authorities on the use of their discretion. Such guidance is crucial in assuring parents that decisions on deferrals are both transparent and consistent. Decisions should reflect the needs of individual children after careful assessment and discussion between schools, parents and the local authority about what is best for the child.The changes require careful preparation. That is why I support the group's recommendation that the new arrangements should be implemented as from the 2001-02 academic year. This means the first eligible children (those becoming four in January or February 2002) will begin their deferred year in August 2002.There are children who will have reached four in January or February this year and whose parents want to defer entry. Although they will not be covered by the new entitlement, I would expect local authorities to continue to make well-informed decisions for them, in the light of full discussions with schools and parents, based upon their individual needs and taking into consideration the new policy which is being introduced.
- those born between September to December
- whose parents are considering deferral.CoSLA and ADES will improve information for parents considering deferral. They will also develop guidance for local authorities on the use of their discretion. Such guidance is crucial in assuring parents that decisions on deferrals are both transparent and consistent. Decisions should reflect the needs of individual children after careful assessment and discussion between schools, parents and the local authority about what is best for the child.The changes require careful preparation. That is why I support the group's recommendation that the new arrangements should be implemented as from the 2001-02 academic year. This means the first eligible children (those becoming four in January or February 2002) will begin their deferred year in August 2002.There are children who will have reached four in January or February this year and whose parents want to defer entry. Although they will not be covered by the new entitlement, I would expect local authorities to continue to make well-informed decisions for them, in the light of full discussions with schools and parents, based upon their individual needs and taking into consideration the new policy which is being introduced.
In the Official Report
No contribution in the Official Report cites S1W-15620 by reference.