SPCB Written Question · S1W-14494 · Session 1
Further to his answer to question S1W-13919 on 20 March 2001, what capital budget has been set aside for the new provision of an underwater…
The question
To ask the Presiding Officer, further to his answer to question S1W-13919 on 20 March 2001, what capital budget has been set aside for the new provision of an underwater pumping system in the water features at the new Parliament building at Holyrood.
The answer
Provision for the underwater pumping system is included in the capital budget for 'landscaping', which covers improvement works to the area surrounding the Holyrood building.
In the Official Report
No contribution in the Official Report cites S1W-14494 by reference.