Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S1W-14377 · Session 1

Further to the answer to question S1W-3338 by Sarah Boyack on 18 January 2000, what action it proposes to take to upgrade or replace bridge…

Answered Asked by Murray Tosh Con Lodged 22 Mar 2001

The question

To ask the Scottish Executive, further to the answer to question S1W-3338 by Sarah Boyack on 18 January 2000, what action it proposes to take to upgrade or replace bridges then and subsequently identified as being unsuitable for reassessment.

The answer

Answered by Sarah Boyack on 5 Apr 2001 · 14 days after it was lodged, on time

Sub-standard bridges will be strengthened or replaced on a prioritised basis as part of the annual trunk road bridge maintenance programme. It is expected this work will take 5 years to complete but the actual timescale will depend on competing priorities and the availability of funding.Not included in this programme are 4 sub-standard bridges that will be replaced as part of other proposed schemes involving the improvement or realignment of the existing trunk road. These structures have been strengthened by propping as an interim measure pending their replacement.

In the Official Report

No contribution in the Official Report cites S1W-14377 by reference.