Further to the answer to question S1W-9148 by Sarah Boyack on 14 September 2000, how local authorities will meet the costs of redundancy pa…

Answered Asked by Fergus Ewing SNP Lodged 23 Jan 2001

The question

To ask the Scottish Executive, further to the answer to question S1W-9148 by Sarah Boyack on 14 September 2000, how local authorities will meet the costs of redundancy payments and any other costs relating to the termination of employment to any local authority employees who lose their employment in the event that the trunk road unit contracts are awarded to private sector bidders if it does not make additional finance available for this purpose.

The answer

Answered by Sarah Boyack on 2 Apr 2001 · 69 days after it was lodged, 55 days after it was due

Trunk road contracts lie outwith the functions of local government and are not catered for in the local government financial settlement. Local authorities have known since1996 when the previous contracts were awarded that they could fail to secure the trunk road work. Some of the management work was lost in 1999. The contracts for the Operating Companies stood to be renewed in 2001. Agency agreements had been awarded without competition and could not therefore extend indefinitely.