Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S1W-10911 · Session 1

Whether the contract for motorway maintenance on the A90 awarded to Yuill & Dodds was awarded by the Scottish Office or by it, when the con…

Answered Asked by Tommy Sheridan SSP Lodged 3 Nov 2000

The question

To ask the Scottish Executive whether the contract for motorway maintenance on the A90 awarded to Yuill & Dodds was awarded by the Scottish Office or by it, when the contract was awarded and how much it was for.

The answer

Answered by Sarah Boyack on 1 Dec 2000 · 28 days after it was lodged, 14 days after it was due

The Scottish Executive has not awarded any motorway maintenance contract to Yuill & Dodds Ltd.

In the Official Report

No contribution in the Official Report cites S1W-10911 by reference.